Schedule and Phasing
Monday, 03 March 2008 19:16
Hits smaller text tool iconmedium text tool iconlarger text tool icon
Tender Dates
Tender for the Pipeline Relocation Contract opened on March 20, 2007 and closed on April 3, 2007.

Tender for the main Interchange Construction Contract (secondary drainage, roadways, retaining walls, and bridges) opened on March 20, 2007 and closed on June 20, 2007.

Contracts Awarded
The single largest contract for the construction of the interchange has been recently awarded to Kiewit Management Co. Kiewit will be responsible for the construction of all grading, retaining walls, noise fences and walls, secondary drainage works, five separate bridges, and all new interchange ramps and roadworks. The work contained in this contract is expected to take three years to complete.

Schedule and Phasing
Construction of the major interchange is scheduled for a four year period from October 2007 through 2011. The majority of interchange construction is expected to be complete in the first three years and the interchange is expected to be functional by the end of 2010. In 2011, the grades and cross-sections of the Gateway Boulevard and Calgary Trail roadways through the interchange area will be modified, thereby completing the work. Construction each year begins in the spring, early to mid April, weather permitting, and ends in late October or early November, depending on the weather. Structural work continues over the winter. See the 2010 Construction Schedule for more information. icon 23 Ave 2010 Construction Schedule (131.15 kB) Please see monthly construction bulletins that describe upcoming work in detail.

iconSeptember 2010 Construction Bulletin (55.56 kB)

iconAugust 2010 Construction Bulletin (55.05 kB)

iconJuly 2010 Construction Bulletin (55.12 kB)

iconJune 2010 Construction Bulletin (264.16 kB)

icon May 2010 Construction Bulletin (55.49 kB)

icon April 2010 Construction Bulletin (55.11 kB)

icon March 2010 Construction Bulletin (55.33 kB)

icon February 2010 Construction Bulletin (55.51 kB)

icon January 2010 Construction Bulletin (54.7 kB)

icon December 2009 23 Ave Construction Bulletin (55.09 kB)

icon November 2009 Construction Bulletin (55.67 kB)

icon October 2009 Construction Bulletin (55.72 kB)

icon September 2009 Construction Bulletin (55.97 kB)

icon August 2009 Construction Bulletin (55.85 kB)

icon July 2009 Construction Bulletin (55.36 kB)

icon June 2009 Construction Bulletin (57.49 kB)

icon May 2009 Construction Bulletin (57.73 kB)

icon April 2009 Construction Bulletin (230.02 kB)

icon March 2009 Construction Bulletin (58.27 kB)

icon February 2009 Construction Bulletin (57.72 kB)

icon January 2009 Construction Bulletin (57.57 kB)

December 2008 Construction Bulletin December 2008 Construction Bulletin 57.82 Kb

November 2008 Construction Bulletin November 2008 Construction Bulletin 58.33 Kb

October 2008 Construction Bulletin October 2008 Construction Bulletin 58.13 Kb

September 2008 Construction Bulletin September 2008 Construction Bulletin 58.89 Kb

August 2008 Construction Bulletin August 2008 Construction Bulletin 57.99 Kb

July 2008 NW Service Road Construction Bulletin July 2008 NW Service Road Construction Bulletin 66.15 Kb

July 2008 Construction Bulletin July 2008 Construction Bulletin 275.18 Kb

June 2008 Construction Bulletin June 2008 Construction Bulletin 57.20 Kb

May 2008 Construction Bulletin May 2008 Construction Bulletin 299.00 Kb

April 2008 Construction Bulletin April 2008 Construction Bulletin 299.02 Kb


Last Updated on Friday, 03 September 2010 13:17